In This Section
Reshaping of the base in preparation for pavement is expected to start next week.
Project Objectives
In 2025, new water main, sanitary sewer main, and storm was installed in preparation for the new street. This year, the concrete pavement will be installed with new curb and gutter and driveway.
Lift station work is roughly 40% complete
The existing lift station on Tower Street was deteriorated with outdated electrical systems and limited access for future upgrades. Contractors are rebuilding the entire lift station system and the building that encloses it.
Project Area
Awarded to Ideal Construction Group
Project Updates
Expected to start early June
Proposed Improvement
1st Avenue SW mill and overlay will rehabilitate the pavement from Crailsheim Road to Klnollwood Drive by milling the old pavement and replacing it with new pavement. The project will also include the rehabilitation of the parking lot for the puppy park.
The outdated water main on Clary Street from McMillan Street to 13th Street will be replaced with new water main.
Awarded to Hulstein Excavating
6th Avenue, from 11th Street to 14th Street, had water main and sanitary sewer main reconstructed in 2025. This year, the storm and pavement in this section will be reconstructed with sidewalk repairs.
Expected to start mid July
The purpose of this project is to reconstruct the outdated sanitary sewer main and water main pipe on 3rd Avenue from 11th Street to 13th Street.
This project will reconstruct the pavement on 10th Avenue, from Tower Street to Whiskey Ditch, and on Tower Street, from 11th Avenue to 10th Avenue. The storm main will also be reconstructed in these sections. Additionally, the existing softball parking lot will be resurfaced with concrete and Tower Street, from Clary Street to 11th Avenue, will be converted into 2 parking lots on the north and south sides of the proposed concessions building.